Jun 22, 2023

Snowy Hydro 2.0 faces challenging conditions

The Snowy Hydro 2.0 management team has confirmed that variable site and geological conditions have impacted the tunnel boring process for the NSW project.

The most impactful being the soft ground encountered, which is delaying tunnel boring machine (TBM) Florence’s progress at Tantangara.

The project team is working towards stabilising the encountered soft ground in order to enable TBM Florence to restart excavating.

Snowy Hydro chief executive officer Dennis Barnes also provided an update on TBM progress across multiple worksites.

“TBM Kirsten has tunnelled 2.9 km to reach the underground power station cavern complex and we now have access to this site from both ends,” Barnes said.

“We shortly expect to commence the 6 km tailrace tunnel that will feed into Talbingo Reservoir and the excavation of intakes at Talbingo and Tantangara are proceeding very well.”

At Lobs Hole, TBM Lady Eileen Hudson completed excavation of the 2.7 km main access tunnel. The machine is currently being reassembled at the Talbingo adit with new components.

It will be launched into the mountain later in the year to excavate the 6 km tailrace tunnel, which will feed into Talbingo Reservoir.

Subscribe to Trenchless Australasia for the latest project and industry news.

2019 VERMEER D40X55DR

$522,500

Toowoomba, QLD

2018 VERMEER PD10

$129,950

Austral, NSW

POWERTECH CORE DRILL STAND (ONLY) TO SUIT PCD-352

$1,395

Coopers Plains, QLD

POWERTECH CORE DRILL 352D

$2,395

Coopers Plains, QLD

POWERTECH CORE DRILL 162D

$1,495

Coopers Plains, QLD

VERMEER HAMMERHEAD

$5,000

Eltham, VIC

DIGGA CORE BARREL CB100

$1,800

POA

per day (HIRE)

Trafalgar, VIC

2011 VERMEER PD10

$95,950

Austral, NSW

1995 DITCH WITCH JT820

$28,000

Dalby, QLD

GRUNDOMATS P-100

$1,500

Eltham, VIC

CSEPEL 4'

$3,000

Toowoomba, QLD

WENCO NA

$2,500

Eltham, VIC

SHARE